Factory rooftop solar

Cut daytime power costs when factories use the most, with typical payback in 4–6 years

Most factories draw the most power between 08:00 and 17:00, exactly when panels produce, so almost every unit is used on site.

What we do

  • Drone roof survey and a structural check by a civil engineer
  • System sized from 12 months of real load data, never oversized
  • All permits handled: ERC, utility and building permit (no factory licence needed since 28 Dec 2024)
  • Installed by our own crews, no subcontractors

Two ways to buy

Invest for the highest return, or sign a power purchase agreement (PPA) with no upfront cost and pay 15–25% less than the grid tariff.

The approvals and installation we handle

  1. Site survey and structural check3–7 days

    Drone roof survey; a licensed civil engineer certifies the roof can carry the panels

  2. System design and single-line diagram7–14 days

    Yield simulated from 12 months of load data, sized to daytime demand

  3. Building permit15–30 days

    Filed with the local authority under Ministerial Regulation No. 72 (2025), which eased rooftop rules

  4. Factory licenceNo longer needed

    No longer required for rooftop solar of any size since 28 Dec 2024

  5. ERC licence or exemption7–15 days

    Self-use systems under 1 MW are exempt from a generation licence but must notify the ERC

  6. Utility interconnection approval30–60 days

    MEA about 30–45 days, PEA about 45–60 days from a complete file

  7. Installation14–45 days

    Our own crews, without stopping your production line

  8. Inspection, meter and commissioning7–15 days

    The utility checks anti-islanding protection, then the system goes live

About 2.8–6.2 months in total; some steps run in parallel and we handle all of them