Commercial roofs are limited, so we design for maximum output per square metre and add real-time monitoring executives can open on their phones.
Suited to
- Shopping malls and community malls
- Hotels and resorts
- Offices pursuing LEED or TREES

Commercial roofs are limited, so we design for maximum output per square metre and add real-time monitoring executives can open on their phones.
Drone roof survey; a licensed civil engineer certifies the roof can carry the panels
Yield simulated from 12 months of load data, sized to daytime demand
Filed with the local authority under Ministerial Regulation No. 72 (2025), which eased rooftop rules
No longer required for rooftop solar of any size since 28 Dec 2024
Self-use systems under 1 MW are exempt from a generation licence but must notify the ERC
MEA about 30–45 days, PEA about 45–60 days from a complete file
Our own crews, without stopping your production line
The utility checks anti-islanding protection, then the system goes live
About 2.8–6.2 months in total; some steps run in parallel and we handle all of them